Predictika · Supply disruption action plans drafted from plant records
A supplier shipment slips. An AI purchasing agent reads the open orders, the stock at each site and the supplier list, and proposes an action plan: a replacement purchase order, a transfer from another site and a new production start. Before anything is released, the agent sends the plan to Predictika, which checks it against a declarative model of what the plant's records say and returns a verdict, every reason and the figures it computed.
This validator models one action plan for one late shipment at a fictional three-site metal fabricator, not just the scenarios shown below. The plant, its suppliers, prices and stock are fictional stand-ins for what a real plant keeps in its ERP: purchase orders, inventory by site, the supplier master and the production schedule.
Any action plan that touches these materials, suppliers, sites and rules is in scope — not only the scenarios pictured here. Not covered: freight cost, customs, multi-line orders, partial deliveries and sites other than the two named. All suppliers, prices, stock and rules are fictional; the orders are fictional.
6 scenarios in 3 groups · each group runs from the agent’s first attempt to the outcome · click one to switch
Illustrative agent statement. The validator receives the structured request below.
Proposing agent: AI purchasing agent (scripted)
Before sending, the agent must call Recorded run
What this means
Our assessment of what the purchasing rules and approval workflow in a typical ERP (reorder points, approved vendor lists, approval limits) do with the same cases. It is a judgment about effort and reliability, not a claim that nothing can be built.
| What the validator caught | Typical purchasing module in an ERP | Predictika |
|---|---|---|
| Whether a replacement is needed at all | Only with workarounds A reorder point fires on stock, not on dates. Whether the late shipment still lands before the order must start is a comparison across a purchase order line, a slip and a production order, which a planner usually does by hand. | The new arrival is compared with the production start on every call, and a plan that spends money when the shipment arrives in time is stopped. |
| Suppliers that depend on the material and the customer program | Only with care An approved supplier list per item is standard; layering the aerospace vendor list and defense domestic melt on top, by customer program, is a manual check or a rule per combination. | Material, supplier and industry are checked together on every call. |
| Stock at another site above its safety stock | Only with workarounds The buyer sees on-hand stock; whether the transfer would eat into the other site's safety stock is netted by hand or in a separate report. | The transfer is checked against what the site can release above its safety stock. |
| Fixing one choice changes the next | Only with workarounds Moving to a slower supplier lengthens the arrival, which moves the earliest production start, which can push past the order's float. Each step is checked separately, after the order is released, by whoever notices. | Supplier, transfer, arrival, start and float are recomputed together, so a fix that opens the next problem is caught in the same answer. |
| An order total and an arrival that have to match the supplier price and lead time | Only with workarounds The ERP prices the order it creates, but the total and arrival an agent typed in its message are not an input, so a total that left out the premium or an arrival taken from the wrong lead time goes through. | The stated total and arrival are compared with the validator's own figures. |
| Every problem returned in one answer | Only with workarounds Rules tend to fire as the order is saved, so a buyer often fixes one error and meets the next. | All findings come back together, whatever order the choices arrived in. |
Every rule is checked on every call, in any order the choices arrive; one problem never hides another. Blocking findings stop the action plan; approval findings need a person to sign off; everything else is computed.
| 1 | The delayed shipment now arrives in 7 days, before production must start in 10 days, so nothing needs to be bought or moved. |
| 2 | The plan brings in 30 tons of the 40 tons short. |
| 3 | A replacement order of 30 tons names no supplier. |
| 4 | The chosen supplier is not on the approved list for this material. |
| 5 | The supplier charges 18 percent above the contract price, over the 15 percent a buyer may accept alone; the purchasing manager approves. |
| 6 | Aerospace work must buy from an approved vendor list supplier that issues mill certificates. |
| 7 | Defense work needs domestic melt material, which only one supplier on the list provides. |
| 8 | A transfer of 10 tons names no source site. |
| 9 | The plan moves 6 tons from a site that holds only 5 tons of this material above its safety stock. |
| 10 | The material arrives in 9 days, after production must start in 6 days, and the plan does not move the start to 10 days or later. |
| 11 | The new production start of 10 days is later than the 8 days the customer order can absorb; planning and sales agree the new date with the customer. |
| 12 | The plan states a purchase order total of $27,000.00, but the contract price with the supplier premium gives $28,620.00. |
| 13 | The plan states material arriving in 2 days, but the supplier lead time and the transfer time give 6 days. |
| 14 | The replacement order totals $164,300.00, above the $150,000.00 a buyer may release alone; the plant controller signs off. |
The recorded result of the validator for each scenario on this page: the request the AI agent sent, the verdict, and every finding, in the order they appear above.
The agent's request. The A36 steel plate shipment, due in 5 days, has slipped 14 days, leaving 40 tons short for aerospace orders that must start production in 3 days. I propose buying 28 tons from Gulf Alloys and moving 12 tons from the Reno plant. The replacement order totals $25,200.00 and the material arrives in 2 days. It is ready to release.
Verdict: Blocked.
The agent's request. The A36 steel plate shipment, due in 5 days, has slipped 14 days, leaving 40 tons short for aerospace orders that must start production in 3 days. I propose buying 20 tons from Northstar Metals and moving 20 tons from the Dayton plant, with production starting in 7 days. The replacement order totals $19,080.00 and the material arrives in 6 days. It is ready to release.
Verdict: Allowed.
The agent's request. The stainless steel 304 shipment, due in 6 days, has slipped 10 days, leaving 50 tons short for defense orders that must start production in 5 days. I propose buying 30 tons from Pinnacle Trading and moving 10 tons from the Reno plant. The replacement order totals $125,550.00 and the material arrives in 3 days. It is ready to release.
Verdict: Blocked.
The agent's request. The stainless steel 304 shipment, due in 6 days, has slipped 10 days, leaving 50 tons short for defense orders that must start production in 5 days. I propose buying 46 tons from Northstar Metals and moving 4 tons from the Dayton plant, with production starting in 7 days. The replacement order totals $151,156.00 and the material arrives in 6 days. It is ready to release.
Verdict: Needs approval.
The agent's request. The carbon steel bar shipment, due in 7 days, has slipped 14 days, leaving 25 tons short for general industrial orders that must start production in 6 days. I propose buying 25 tons from Apex Steel, with production starting in 7 days. The replacement order totals $27,825.00 and the material arrives in 9 days. It is ready to release.
Verdict: Blocked.
The agent's request. The carbon steel bar shipment, due in 7 days, has slipped 14 days, leaving 25 tons short for general industrial orders that must start production in 6 days. I propose buying 11 tons from Northstar Metals and moving 14 tons from the Reno plant. The replacement order totals $12,243.00 and the material arrives in 6 days. It is ready to release.
Verdict: Allowed.
The text of the narrated walkthrough, step by step.