Predictika · Ethernet connectivity orders
An AI sales agent prepares an order for a Colt On Demand Ethernet port with one or more circuits. Before it goes out, the agent sends it to Predictika, which checks it against a declarative model of the published port and circuit rules and returns a verdict and every reason.
This validator models Colt On Demand Ethernet port and circuit orders, not just the scenarios shown below.
Any Colt On Demand Ethernet order that touches these rules is in scope — not only the scenarios pictured here. Not covered: prices (Colt publishes only two example port prices and no circuit price list, so this validator produces no price build-up or line-item quote), metro zones, nearnet buildings, cloud ports, internet on demand and other Colt products. Assumptions: the treatment of booked bandwidth above the port speed as a matter for approval is this model's reading of the overbooking note, and the key data centre rule for circuits above 10 Gbps comes from the published connections page.
6 scenarios in 3 groups · each group runs from the agent’s first attempt to the outcome · click one to switch
Illustrative agent statement. The validator receives the structured request below.
Proposing agent: AI sales agent (scripted)
Before sending, the agent must call Recorded run
What this means
Our assessment of what a typical rules-based CPQ (product rules, price rules and validation rules, as in Salesforce CPQ) does with the same cases. It is a judgment about effort and reliability, not a claim that nothing can be built.
| What the validator caught | Typical rules-based CPQ | Predictika |
|---|---|---|
| Port terms that depend on the location type | Only with care Each location type has its own term rule, so the term check has to sit beside the port type on every line. | The port type and its term are in one request and checked together on every call. |
| Interfaces that depend on the port speed | Only with care A product rule per speed and interface pairing; each new interface is another rule to maintain. | Port speed and interface travel together and the pairing is checked on every call. |
| Circuits that are limited by the port they sit on | Only with workarounds The circuit speed, the number of circuits and the port speed are on different lines, so the comparisons need cross-line rules. | Port and circuits are one request; speed, count and total are compared together. |
| Terms and downgrades that depend on the pricing model | Only with workarounds Flex and Traditional circuits have different term lists and different downgrade rules, which multiplies the rules. | The pricing model and term are fields of the request and are checked against their own lists on every call. |
| Every problem returned in one answer | Only with workarounds Rules tend to fire as the order is saved or a step is completed, so a rep often fixes one error and meets the next. | All findings come back together, whatever order the choices arrived in. |
Every rule is checked on every call, in any order the choices arrive; one problem never hides another. Blocking findings stop the quote; approval findings need a person to sign off; everything else is computed.
| 1 | The order has no circuit on the port. |
| 2 | On-net, hybrid on-net and nearnet ports come in 1, 10 and 100 Gbps; a 5,000 Mbps port is not available. |
| 3 | Off-net ports run from 10 Mbps to 10 Gbps; a 100,000 Mbps port is not available. |
| 4 | Off-net ports run from 10 Mbps to 10 Gbps; a 5 Mbps port is not available. |
| 5 | A 10 Mbps circuit cannot be faster than the 5 Mbps port. |
| 6 | On-net data centre ports are available on a 3 or 12 month contract; the order has 6 months. |
| 7 | Ports at enterprise locations need a minimum 12 month commitment; the order has 6 months. |
| 8 | Off-net and hybrid on-net ports are available on 12 to 60 month contracts; the order has 72 months. |
| 9 | Off-net and hybrid on-net ports are available on 12 to 60 month contracts; the order has 6 months. |
| 10 | A circuit speed of 75 Mbps is not available; speeds run 10 Mbps to 10 Gbps in published steps, plus 20, 30 and 40 Gbps between key data centres. |
| 11 | A 2,000 Mbps circuit cannot be faster than the 1,000 Mbps port. |
| 12 | A 40,000 Mbps circuit is available only between key data centres and on a 100 Gbps port. |
| 13 | A 20,000 Mbps circuit is available only between key data centres and on a 100 Gbps port. |
| 14 | The chosen optical or electrical interface is not available at the 10,000 Mbps port speed; 1 Gbps uses 1,000Base-LX, SX or T, 10 Gbps uses 10GBASE-LR or SR, and 100 Gbps uses 100GBASE-LR4 or SR4. |
| 15 | This circuit pricing model does not offer a term of 5 months; Flex offers 1 hour or 3, 6, 12, 24 or 36 months, and Traditional offers 12, 24 or 36 months (0 means 1 hour). |
| 16 | This circuit pricing model does not offer a term of 3 months; Flex offers 1 hour or 3, 6, 12, 24 or 36 months, and Traditional offers 12, 24 or 36 months (0 means 1 hour). |
| 17 | This circuit pricing model does not offer a term of 0 months; Flex offers 1 hour or 3, 6, 12, 24 or 36 months, and Traditional offers 12, 24 or 36 months (0 means 1 hour). |
| 18 | Bandwidth can be flexed down only on a 1 hour Flex contract; other circuits can be upgraded but not downgraded. |
| 19 | An open port carries one circuit; 4 circuits need Add VLAN or Filter VLAN mode. |
| 20 | An off-net port supports a single circuit as standard; the order has 2 circuits. |
| 21 | Only fibre cross connects are supported; copper cross connects are not. |
| 22 | The circuits total 12,000 Mbps on a 10,000 Mbps port; overbooking is available on request for NNI ports only, so a person should confirm. |
| 23 | A 5,000 Mbps circuit cannot be faster than the 1,000 Mbps port. |
The recorded result of the validator for each scenario on this page: the request the AI agent sent, the verdict, and every finding, in the order they appear above.
The agent's request. Please order an on-net data centre port at 10 Gbps on a 6-month contract with 1000Base-SX interface and a copper cross connect, carrying 6 circuits of 500 Mbps each on Traditional pricing with a 6-month term, in open-port mode. It is ready to send.
Verdict: Blocked.
The agent's request. Please order an on-net data centre port at 10 Gbps on a 12-month contract with 10GBASE-LR interface and a fibre cross connect, carrying 6 circuits of 500 Mbps each on Flex pricing with a 12-month term, in Add VLAN mode. It is ready to send.
Verdict: Allowed.
The agent's request. Please order an off-net port at 1 Gbps on a 6-month contract with 1000Base-LX interface and a fibre cross connect, carrying 3 circuits of 200 Mbps each on Flex pricing with a 12-month term, in Add VLAN mode. It is ready to send.
Verdict: Blocked.
The agent's request. Please order an off-net port at 1 Gbps on a 24-month contract with 1000Base-LX interface and a fibre cross connect, carrying 1 circuit of 200 Mbps on Flex pricing with a 12-month term, in Add VLAN mode. It is ready to send.
Verdict: Allowed.
The agent's request. Please order an on-net data centre port at 10 Gbps on a 12-month contract with 10GBASE-LR interface and a fibre cross connect, carrying 1 circuit of 40 Gbps on Flex pricing with a 12-month term, in Add VLAN mode. It is ready to send.
Verdict: Blocked.
The agent's request. Please order an on-net data centre port at 100 Gbps on a 12-month contract with 100GBASE-LR4 interface and a fibre cross connect, carrying 1 circuit of 40 Gbps on Flex pricing with a 12-month term, in Add VLAN mode, between two key data centres. It is ready to send.
Verdict: Allowed.