Predictika · Upright Multi-Position MRI
An AI sales agent prepares an order for a FONAR UPRIGHT Multi-Position MRI together with the customer's site plan: magnet room, equipment room, power, cooling, the heaviest patient and the coil packages. Before it goes out, the agent sends it to Predictika, which checks it against a declarative model of the figures on Fonar's public siting and specifications pages and returns a verdict and every reason.
This validator models the figures on Fonar's public Upright MRI siting and specifications pages (fonar.com, read in October 2026), not just the scenarios shown below.
Any order for this scanner that touches these rules is in scope — not only the scenarios pictured here. Not covered: prices (Fonar publishes none, so this validator produces no price build-up), the FONAR 360 and OPEN-SKY scanners, floor loading and delivery routes, software options, service contracts, and whether the Advanced package needs the Standard package (the pages do not say).
7 scenarios in 3 groups · each group runs from the agent’s first attempt to the outcome · click one to switch
Illustrative agent statement. The validator receives the structured request below.
Proposing agent: AI sales agent (scripted)
Before sending, the agent must call Recorded run
What this means
Our assessment of what a typical rules-based CPQ (product rules, price rules and validation rules, as in Salesforce CPQ) does with the same cases. It is a judgment about effort and reliability, not a claim that nothing can be built.
| What the validator caught | Typical rules-based CPQ | Predictika |
|---|---|---|
| Site limits that sit beside the product | Only with workarounds Room area, ceiling, three separate power supplies and two heat loads are site facts, not product options. A rules-based CPQ has no natural place for them and they are usually left to a site survey. | The siting figures are data; each order is compared with every one of them on every call. |
| Several shortfalls at once | Only with care A suite can fail on area, ceiling, amperage and cooling together; fixing one shows the next. | All site limits are evaluated together and every shortfall is reported in one answer. |
| Coils by package | Only with care Each coil belongs to a Standard or Advanced package; a rep can order a coil without the package that contains it. | The coil, the belt size and the packages in the order are checked together on every call. |
| Figures the order states | Only with workarounds A stated room area or connected load has to be recomputed from the room dimensions and from three consumption figures, and nothing in a plain configurator does that. | The stated figures are fields in the request, compared with the computed values on every call. |
| Items Fonar does not list | Only with workarounds A coil that is on neither package list is neither valid nor invalid in a rules table; it is either blocked wrongly or let through. | It is sent to a person with the reason, instead of being guessed. |
| Every problem returned in one answer | Only with workarounds Rules tend to fire as the order is saved or a step is completed, so a rep often fixes one error and meets the next. | All findings come back together, whatever order the choices arrived in. |
Every rule is checked on every call, in any order the choices arrive; one problem never hides another. Blocking findings stop the order; approval findings need a person to sign off; everything else is computed.
| 1 | The magnet room is 493 sq ft; the Fonar siting page lists a minimum installed area of 504 sq ft (28 ft x 18 ft). |
| 2 | The magnet room ceiling is 10 ft; the Fonar siting page lists a required ceiling height of 11 ft. |
| 3 | The equipment room is 238 sq ft; the Fonar siting page lists a minimum installed area of 240 sq ft (12 ft x 20 ft). |
| 4 | The magnet supply is 208 V; the Fonar siting page lists 480 V, three-phase. |
| 5 | The magnet supply is 124 A; the Fonar siting page lists 125 A at 480 V, three-phase. |
| 6 | The system racks need a 120/208 V three-phase supply according to the Fonar siting page. |
| 7 | The system rack supply is 199 A; the Fonar siting page lists 200 A at 120/208 V, three-phase. |
| 8 | The chiller supply is 208 V; the Fonar siting page lists 480 V, three-phase. |
| 9 | The chiller supply is 99 A; the Fonar siting page lists 100 A at 480 V, three-phase. |
| 10 | The magnet room cooling is 29999 BTU, below the magnet room heat load of 30,000 BTU the Fonar siting page lists; a person should confirm with Fonar that the cooling covers it. |
| 11 | The equipment room cooling is 47999 BTU, below the equipment room heat load of 48,000 BTU the Fonar siting page lists; a person should confirm with Fonar that the cooling covers it. |
| 12 | The heaviest patient is 501 lb; the Fonar specifications page lists a patient weight limit of 500 lb. |
| 13 | The order has a 50 inch spine and body belt; the Fonar specifications page lists 45, 55 and 65 inch belts. |
| 14 | A coil or belt on the order is listed in the Standard Coil Package on the Fonar specifications page and the order does not include that package; a person should confirm with Fonar that it is supplied without the package. |
| 15 | A coil on the order is listed in the Advanced Coil Package on the Fonar specifications page and the order does not include that package; a person should confirm with Fonar that it is supplied without the package. |
| 16 | A requested coil is not among the coils the Fonar specifications page lists for the Standard and Advanced Coil Packages; a person should confirm it with Fonar. |
| 17 | The order states a magnet room of 500 sq ft; the room length and width give 504 sq ft. |
| 18 | The order states a connected load of 160 kVA; the Fonar siting page power consumption figures (100 kVA magnet, 20 kVA system racks, 47 kVA chiller when running) add up to 167 kVA. |
The recorded result of the validator for each scenario on this page: the request the AI agent sent, the verdict, and every finding, in the order they appear above.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 17 ft with a 10 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 125 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 48,000 BTU for the equipment room. The heaviest patient is 450 lb. Coil packages: Standard. Coils wanted: a 55 inch spine and body belt, a flexible cervical coil, a solenoid wrist coil. The order states a magnet room of 504 sq ft and a total connected load of 167 kVA. It is ready to send.
Verdict: Blocked.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with a 10 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 125 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 48,000 BTU for the equipment room. The heaviest patient is 450 lb. Coil packages: Standard. Coils wanted: a 55 inch spine and body belt, a flexible cervical coil, a solenoid wrist coil. The order states a magnet room of 504 sq ft and a total connected load of 167 kVA. It is ready to send.
Verdict: Blocked.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with an 11 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 125 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 48,000 BTU for the equipment room. The heaviest patient is 450 lb. Coil packages: Standard. Coils wanted: a 55 inch spine and body belt, a flexible cervical coil, a solenoid wrist coil. The order states a magnet room of 504 sq ft and a total connected load of 167 kVA. It is ready to send.
Verdict: Allowed.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with an 11 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 100 A, the system racks 120/208 V three-phase at 200 A, and the chiller 208 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 40,000 BTU for the equipment room. The heaviest patient is 480 lb. Coil packages: Standard. Coils wanted: a 65 inch spine and body belt, a Signal-Plus universal coil. The order states a total connected load of 167 kVA. It is ready to send.
Verdict: Blocked.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with an 11 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 150 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 52,000 BTU for the equipment room. The heaviest patient is 480 lb. Coil packages: Standard. Coils wanted: a 65 inch spine and body belt, a Signal-Plus universal coil. The order states a total connected load of 167 kVA. It is ready to send.
Verdict: Allowed.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with an 11 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 125 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 48,000 BTU for the equipment room. The heaviest patient is 480 lb. Coil packages: Standard. Coils wanted: a 50 inch spine and body belt, a quadrature knee coil, a quadrature head coil. The order states a magnet room of 504 sq ft. It is ready to send.
Verdict: Blocked.
The agent's request. Please order the FONAR UPRIGHT Multi-Position MRI for our imaging center. The magnet room is 28 ft by 18 ft with an 11 ft ceiling, and the equipment room is 20 ft by 12 ft. Power: the magnet gets 480 V three-phase at 125 A, the system racks 120/208 V three-phase at 200 A, and the chiller 480 V three-phase at 100 A. Cooling is 30,000 BTU for the magnet room and 48,000 BTU for the equipment room. The heaviest patient is 480 lb. Coil packages: Standard and Advanced. Coils wanted: a 55 inch spine and body belt, a quadrature knee coil, a quadrature head coil. The order states a magnet room of 504 sq ft. It is ready to send.
Verdict: Allowed.
The text of the narrated walkthrough, step by step.