Predictika · surface mining haul truck quotes, in the style of Komatsu
An AI sales agent prepares a quote for a surface mining haul truck, with the order total it expects. Before the quote goes out, the agent sends it to Predictika's validator, which checks the truck, body, tire set, material density, site temperature, tire load, site altitude, loading bucket and number of trucks against each other, compares the total the agent states with the one it computes, and returns a verdict with every reason in one pass. All prices and limits are Predictika estimates in US dollars, not Komatsu list prices.
This validator checks any quote for these trucks, bodies, tire sets and sites, not just the scenarios shown below.
Any quote for these trucks, bodies, tire sets and sites is in scope, not only the scenarios pictured here. Not checked: other Komatsu product lines such as hydraulic mining shovels, dozers, parts and services, real list prices or lead times, haul road design, and tax or multi-currency quoting.
6 scenarios in 3 groups · each group runs from the agent’s first attempt to the outcome · click one to switch
Illustrative agent statement. The validator receives the structured request below.
Proposing agent: AI sales agent (scripted)
Before sending, the agent must call Recorded run
What this means
Our assessment of what a typical rules-based CPQ (product rules, price rules and validation rules, as in Salesforce CPQ or Conga) does with the same cases. It is a judgment about effort and reliability, not a claim that nothing can be built.
| What the validator caught | A rules-based CPQ | Predictika |
|---|---|---|
| A cold site needs a heated body | Only with care A site condition has to select or exclude a body option, so a table of exceptions grows with every new site limit. | The site temperature is compared with the body property directly, in the same request. |
| Altitude and kit | Only with workarounds A site value, a truck limit and an optional kit interact, and the rule is usually written once per truck class. | Altitude, the truck limit and the kit are evaluated together on every call. |
| Tire load against the rating | Only with care A customer number against a rating with a near-limit review band is rarely held in option rules. | Both the hard limit and the review band are checked. |
| The total the agent states | Only with workarounds Comparing a stated figure with a computed one means a separate rule per quote layout, and price rules rarely run on stated figures. | The stated net total is a field in the request and is checked against the computed total. |
| Every problem returned in one answer | Only with workarounds Rules tend to fire as the quote is saved, so a rep often fixes one error and meets the next. | All findings come back together, whatever order the choices arrived in. |
Every rule is checked on every call, in any order the choices arrive; one problem never hides another. Blocking findings stop the quote; approval findings need a person to sign off; everything else is computed.
| 1 | The material density times the body volume must not exceed the truck's rated payload by more than 10 percent; between 100 and 110 percent needs a review. |
| 2 | A site temperature below minus 10 C needs the exhaust heated body. |
| 3 | The tire load (TKPH) must not exceed the rating of the tire set; above 90 percent of the rating needs a review. |
| 4 | A site above the truck's altitude limit needs the altitude kit; a site above 4500 m needs an engine derate review even with the kit. |
| 5 | The loading bucket must fill the truck in 2 to 8 passes; outside 3 to 6 passes is not a good match and needs a review. |
| 6 | A quote covers 1 to 20 trucks. |
| 7 | A volume discount applies from 5 trucks (3 percent) and from 10 trucks (5 percent). |
| 8 | A total discount over 5 percent needs the sales director; over 10 percent is blocked. |
| 9 | An order value over USD 20,000,000 needs a deal desk review. |
| 10 | The net total stated in the quote must match the total computed from the line items. |
The recorded result of the validator for each scenario on this page: the request the AI agent sent, the verdict, and every finding, in the order they appear above.
The agent's request. Please check this quote for the Cerro Alto Gold Project: one 830E class haul truck with a standard rock body and standard tires, loaded by a 45 ton bucket, at a 4000 m site. The total for the order is USD 4,210,000.00. The quote is ready to send.
Verdict: Blocked.
The agent's request. Please check this quote for the Cerro Alto Gold Project: one 830E class haul truck with a standard rock body, standard tires and the altitude kit, loaded by a 45 ton bucket, at a 4000 m site. The total for the order is USD 4,250,000.00. The quote is ready to send.
Verdict: Allowed.
The agent's request. Please check this quote for the Tamarack Ridge Copper Mine: one 830E class haul truck with a standard rock body and standard tires, loaded by a 45 ton bucket, at a 1500 m site that sits at minus 15 C. The total for the order is USD 4,210,000.00. The quote is ready to send.
Verdict: Blocked.
The agent's request. Please check this quote for the Tamarack Ridge Copper Mine: one 830E class haul truck with an exhaust heated rock body and standard tires, loaded by a 45 ton bucket, at a 1500 m site that sits at minus 15 C. The total for the order is USD 4,255,000.00. The quote is ready to send.
Verdict: Allowed.
The agent's request. Please check this quote for the Granite Basin Iron Ore Operation: one 830E class haul truck with a standard rock body and standard tires, loaded by a 45 ton bucket, at a 1500 m site. The total for the order is USD 3,789,000.00. The quote is ready to send.
Verdict: Blocked.
The agent's request. Please check this quote for the Granite Basin Iron Ore Operation: one 830E class haul truck with a standard rock body and standard tires, loaded by a 45 ton bucket, at a 1500 m site. The total for the order is USD 4,210,000.00. The quote is ready to send.
Verdict: Allowed.
The text of the narrated walkthrough, step by step.